Painted stage area and prepared for installation of wood flooring
Finished installation of exterior glass on Southwest corner
Finished installation of seats in balcony areas
February 1, 2021
Installed drywall around event floor and balcony areas
Painted structural steel, railings and metal mesh system
Continued applying finishes to bathroom and indoor bar areas
January 15, 2021
Installed elevator in public lounge area
Began painting black box and metal mesh sections
Prepared balconies for upcoming seat installation
December 2020
Installed and turned on ceiling lights over stage and balconies
Began painting walls and installing metal mesh wall system
Began laying tile in bathrooms
November 2020
Installed glass panels on Southeast and Southwest corners
Reached exterior completion milestone
Supplied permanent power to interior
Began installing drywall in event floor rooms
October 2020
Installed railings on balcony risers
Treated ceiling with acoustical spray
Poured interior stairs and Race Street curbs
Began installation of thermal panels and perforated metal panels
September 2020
Completed high roof of venue
Installed panels on West side
Poured stage area on Level 2
Began installation of pipes, acoustic treatment, and fans
August 2020
Installed uppermost piece of steel and celebrated topping out
Continued laying panels on South Mechanical roof
Began setting frames for two escalators with crane
July 2020
Set trusses for roof framing and began laying material for upper roof
Installed prefab panels for exterior skin on South end of building
Completed masonry work on first level of venue
Began erecting steel structure on North end of venue
June 2020
Installed precast risers on both balconies as foundation for seating
Poured concrete floors for concession, restroom, and lobby areas
Began exterior framing to support installation of trusses
May 2020
Erected steel structure to frame South side of building
Poured concrete slab on metal decks to support balcony on Levels 4 & 5
Began mechanical construction and insulation, drywall, & acoustical ceiling projects
April 2020
Finished pouring concrete for third level of the venue which will support the box office and venue entry
Received first delivery of structural steel and began work on structure that will support the two balconies
Commenced masonry work on stage, partition walls, and egress stairs inside the venue
March 2020
Finished pouring concrete podium for first level of the venue
Began pouring columns to support box office and venue entry levels
Continued the rough-ins for the mechanical, electrical, and plumbing systems
February 2020
Mechanical, electrical and plumbing systems (MEPS) rough-ins began. These are the pathways that will eventually hold various service lines like sanitation, electric, water and more.
Started the elevated concrete slab
Contact Us
Message Not Sent
Message Sent!
Thank you for your message! We will get back to you shortly.